Pioneer Street Extension
City of Ridgefield
The project included four acres of clearing & grubbing, 8,800 Cubic Yards of roadway excavation, 3,100 Cubic Yards of excavation for four stormwater facilities, 5,000+ LF of utility line installation (Water, Sewer, Storm), 47 precast structures, 880 LF of Joint Utility Trenching & Coordination which contained services from NW Natural, Comcast, Lumen, City of Ridgefield, and Clark Public Utilities. The project also consisted of roundabout construction, which contained 3,590 SY of textured and pigmented concrete, 5,400 LF of concrete curb, 2,050 SY of sidewalk, 16 Curb Ramps, 300 basalt columns, four decorative landscape walls with lettering, 3,000 tons of asphalt, a traffic signal system in the intersection of S 5th St & S Union Ridge, a rectangular rapid flashing beacon system at crosswalks, installation of an illumination system at the roundabout & intersection, 2,500+ plants were planted, over an acre of ground was seeded, and 1,700+ LF of fencing was installed.
City of Ridgefield
City of Ridgefield